试题52(2010年下半年试题73)
Changes may be requested by any stakeholder involved with the project,but changes can be authorized only by (73) .
(73)A.executive IT manager
B.project manger
C.change control board
D.project sponsor
试题52分析
变更可能来自于任何项目干系人,但变更的决策权在CCB。
试题52答案
(73)C