试题38(2008年下半年试题73)
The Estimate Activity Resource process is closely coordinated with the (73) process.
(73)A.Estimate Costs
B.Sequence Activities
C.Plan Communications
D.Conduct Procurements
试题38分析
活动资源估算过程与成本估算过程密切相关。
试题38答案
(73)A