试题33(2008年上半年试题73)
The project maintains a current and approved set of requirements over the life of the project by doing the following:
· (73) all changes to the requirements.
· Maintaining the relationships among the requirements,the project plans,and the work products
· …
(73)A.Monitoring
B.Managing
C.Gathering
D.Reducing
试题33分析
项目在整个生命周期中,通过下列活动来维护一组当前的和被验证的需求:
· 管理所有需求变更。
· 维护需求、项目计划和工作产品之间的关系。
· ……
试题33答案
(73)B