试题15(2005年下半年试题74)
(74) is the budgeted amount for the work actually completed on the schedule activity or WBS component during a given time period.
(74)A.Planned value
B.Earned value
C.Actual cost
D.Cost variance
试题15分析
挣值是在给定时期内按进度活动或WBS部件所实际完成工作的预算值。
试题15答案
(74)B